On July 14, the Thailand Universal Data Center Project reached a significant milestone as the first steel structure component of Building B successfully passed inspection.


The inspection was conducted under the full supervision of all three parties involved, following a four-step procedure of "listening, reviewing, inspecting, and evaluating." First, the construction progress report was presented to provide a comprehensive understanding of the construction process and quality control measures. Subsequently, the inspection team entered the facility to conduct on-site checks of key aspects, including steel structure components, dimensional specifications, and fireproof and anti-corrosion coatings. At the same time, detailed reviews of completion documents were carried out to verify the completeness of material test reports and other records. After a comprehensive evaluation, the Thai delegation unanimously confirmed that all indicators met design and regulatory requirements, marking a phased achievement in the construction of the Thailand Universal Data Center Project.


Since the official commencement of construction, all builders from Zhongwei Kejian have overcome numerous challenges, adhering to high standards and quality as their core principles. Through hard work and dedication, they have efficiently completed the project tasks with excellence. In the next phase, Zhongwei Kejian will maintain its high morale and rigorous approach, striving to advance follow-up work and bring the project to a successful conclusion. Moving forward, the company will continue to build on this momentum, crafting new chapters with the craftsmanship and spirit of an iron-willed team.